First tramway project
teaches
Concrete supports built for the first of five metro lines in
“You guys just sit there and
quarrel. Money [compensation] will have to be paid, so the project can’t be
delayed any further. It’s time for a breakthrough to facilitate the process,”
he told attendees of the meeting on February 24 with the Hanoi Metropolitan
Railway Management – the investor of the tramway project connecting the Hanoi
Railway Station and Tu Liem District.
The 12.5 kilometers (7.8 miles)
tramway project, which broke ground in 2010, was originally scheduled for
completion in 2015 before it was delayed to 2017 and recently to 2018.
Thao instructed Tu Liem District
authorities to complete site clearance by late April and the investor to
reach an agreement with the project consultant on compensation in March.
“If there is no improvement, the
city will launch an inspection into individuals and entities involved,” he
said.
But he said there would be no clear
deadline for the project without pointing out the culpability of individuals
involved. The 2018 deadline is still a challenge, he said.
Costly trial
At the February 24 meeting, Thao
said the tramway is the city’s first such project - a kind of “trial” - thus
relevant agencies have no experience to build upon in implementing it.
He also said the plans were unclear
and related agencies were not coordinating well with each other.
Due to delays, the project’s consultant,
The company also proposed upping the
contract value from €22 million to €43 million for extended consultation.
The project investor is negotiating
with Systra for €1.3 million in compensation and an additional amount for
ongoing consultancy.
In an editorial on February 25, Giao
Duc Viet
“No matter how much it [compensation
and increasing costs] is, who is responsible when residents’ money is
burned?”
It said the Systra’s recent proposed
amount for extended consultancy is much more than total development
investment for a province like
“A familiar question will be raised:
who is responsible? The answer may be like Thang Van Phuc, former deputy minister
of the interior, once said: ‘In many cases, people will blame the system’,”
the editorial said.
Displacement problem
According to the project investor,
one of the major hurdles was site clearance for the main construction
packages.
Tu Liem District authorities have
approved a compensation plan for only 42 of 143 cases at the terminal in
package 1.
Up to 13 percent of the area for
package 4 is still not cleared for construction.
Package 2 – constructing mid-way
stops – has been halted due to the lack of a consultant since a contract with
Systra ended last November.
More and more delays
Compensation and increasing costs
incurred by project delays have become more common in
Last year, slow site clearance
increased the cost of a package to build the
Hiroshi Asakami, the project manager
of the Japanese-owned Tokyu Corporation, said the money was additional fees
caused by changes in the scope of works.
Tokyu was contracted to build a road
leading to the bridge that will span the
Recently,
This land is whose land?
According to a recent editorial in Thanh
Nien newspaper, all late infrastructure projects use the same excuse that
local residents refuse to accept compensation.
“Seventy percent of complaints
involve land, of which 80 percent involve compensation and resettlement… But
it is strange that land revocation policies remain unchanged for 15 years and
have been implemented for all localities and all projects,” the editorial
said.
“Site clearance for property
projects is faster than in public service projects because the investors in
property projects are able to ‘grease payment’ for the site clearance team
and for displaced residents,” it said.
The editorial also criticized
wrongdoings in site clearance that frustrated affected residents.
For example, at the Hanoi Beltway 2
project, residents did not accepted site clearance plan because they said
that some people had modified the plan to avoid land owned by certain people.
“A fair and transparent sharing of
benefits in all cases is always a solution for the site clearance problem,”
the editorial said.
“If no one is responsible for the
money spent from the state exchequer in compensation of billions of dong to
the consultant for late site clearance, the problem will remain
unsolved.”
Like us on Facebook and scroll
down to share your comment
|
Thứ Hai, 3 tháng 3, 2014
Đăng ký:
Đăng Nhận xét (Atom)
Không có nhận xét nào:
Đăng nhận xét