Tisco reaches agreement with Chinese contractor to resume
multimillion-dollar project
The long-delayed Thai Nguyen
iron and steel plant-phase 2 will be revised after the investor Tisco and the
Chinese contractor reached a compromise in resuming the unfinished
construction.
MCC has agreed to finish
the construction of Thai Nguyen iron and steel plant-phase 2
After numerous failures to lure the
Chinese contractor China Metallurgical Group Corporation (MCC) back to the
negotiation table, the parties have managed to resolve their differences.
Accordingly, MCC agreed to complete
the construction of the unfinished stages of the project, according to the
signed engineering, procurement and construction (EPC) contract, with the
best quality and price.
Previously, MCC evaluated that a
total investment capital of $105 million will be necessary for the
construction of the remaining stages, including expenditures for equipment
suppliers, and sent the evaluation report to Tisco.
Besides, the management board of the
project and MCC reached a compromise on specific plans to solve existing
problems relating to 14 Vietnamese sub-contractors.
Along with co-operating with MCC to
resume the construction, Tisco also signed a contract with a consultancy firm
to evaluate Thai Nguyen iron and steel plant-phase 2 as well as assess
project efficiency. Accordingly, the consultancy firm will complete the
verification before October 30, 2017.
Furthermore, Tisco is building a
detailed plan to increase its chartered capital, complying with the
regulation of not using investment capital from state-run VNSteel.
Previously, at its 2017 extraordinary general shareholders’ meeting held in
mid-May, shareholders approved to issue shares worth up to VND2 trillion
($87.2 million) to increase its chartered capital.
The plant’s construction was kicked
off in 2007 under an EPC contract with the initial investment capital of
VND3.8 trillion ($170.4 million) but was delayed due to the global financial
crisis. In 2009 it was resumed, however, expected costs increased to VND8
trillion ($361.4 million).
In 2012, MCC decided to abandon the
project and returned to China because the investor had difficulty arranging
capital after disbursing more than VND4.5 trillion ($216.35 million). Thus,
the project’s construction has been delayed for four years.
In March 2016, Tisco announced that
it can arrange the necessary finances to continue the construction. The
second phase of the expansion of Thai Nguyen iron and steel plant is one of
the twelve loss-marking projects of the Ministry of Industry and Trade.
VIR
|
Thứ Sáu, 29 tháng 9, 2017
Đăng ký:
Đăng Nhận xét (Atom)
Không có nhận xét nào:
Đăng nhận xét