Ruins as frames and concrete
collapsed at a
The transport ministry on Sunday afternoon
suspended several officials and a subcontractor in charge of a
Chinese-contracted Hanoi railway project where a scaffolding and mass of
concrete collapsed in the morning.
The
ministry barred Vietnam Technology Consultant and Construction Investment JSC
(Vinacontech) from all work at Cat Linh-Ha Dong elevated railway.
Vinacontech,
which was directly in charge of the part, is blamed for the incident that
took place at 4 am Sunday, when the scaffolding and a frame under
construction at Ha Dong terminal collapsed while concrete was being poured
in, smashing several parked cars.
“The
accident caused no casualties,” the ministry said in its statement.
The
ministry suspended Ta Trung Van, a consultant overseeing the terminal, and
censured the project’s chief consultant Diem Chi Cuong. Their responsibility
in the accident is being probed further.
Nguyen Van
Bao, deputy director of the Railway Project Management Unit, was also
suspended pending further investigation.
The
ministry has ordered the main contractor, China Railway Sixth Group Co. Ltd.,
a Chinese state-owned enterprise, to urge its subcontractors to expedite the
clearance of the rubble and ensure safety for travelers.
Traffic in
the area has resumed.
Workers try to retrieve a taxi from iron frames that collapsed at a
Hanoi elevated railway project on December 28, 2014. Photo credit: VietNamNet
“The main
contractor has to take full responsibility and cover all the cost incurred by
the accident,” the ministry said in its statement.
Nguyen Hong
Truong, vice minister of transport, has arrived at the site to direct the
cleanup of the mess and the ongoing investigation.
“We are
scrambling to handle the incident by today,” Truong said.
Deputy
Prime Minister Hoang Trung Hai and Transport Minister Dinh La Thang have been
urging the project’s managers to speed up for trial run in October next year
and to open the railway to traffic by the end of next year.
The
officials have panned the Chinese contractor for various delays that have
added US$339 million to the project's cost. Its initial estimation
in 2008 was US$552 million.
The Cat
Linh-Ha Dong elevated railway project was first scheduled to break ground in
August 2008 and finish in November 2013.
State-owned
Vietnam Railways was tasked with overseeing the project, which only started
in October 2011.
The 13-km
of elevated track was planned to stretch from Cat Linh Street to Yen Nghia
Bus Station in Ha Dong District making stops at 12 stations.
On November
6, another accident at the project killed bike rider Nguyen Nhu Ngoc, 33, on
the spot.
A crane was
lifting a steel rod when its cable suddenly broke, and the rod fell and hit
several motorbikes, injuring three other people.
By Thai Son, Thanh Nien News
|
Chủ Nhật, 28 tháng 12, 2014
Đăng ký:
Đăng Nhận xét (Atom)
Không có nhận xét nào:
Đăng nhận xét