Electricity sector gets BOT
boost
Vietnam-based manufacturers are
looking forward to a more stable power supply in the near future, with a
series of build-operate-transfer power plants speeding up and coming online,
and many foreign investors showing strong interest in the segment due to the
high demand.
Last week, the operators of the
Chinese-invested, 1,200-megawatt (MW) build-operate-transfer (BOT) Vinh Tan 1
thermal power project reported to Vietnam’s government that they will be
finished 11 months ahead of schedule, as the $1.75 billion plant, located in
the south-central province of Binh Thuan, is expected to start its first
turbine in 2018 and the second in 2019.
Jointly invested by China Southern
Power Grid, China Power International Holdings, and Vinacomin Power, the Vinh
Tan 1 thermal power project is one in a lineup of key power projects in the
government’s Power Development Master Plan VII, aimed at meeting Vietnam’s
dramatically rising power demand during 2010-2020, with a vision toward 2030.
Vinh Tan 1 is the biggest power
plant invested by a Chinese investor in Vietnam.
Tran Viet Ngai, chairman of the
Vietnam Energy Association, said that the successful completion of the BOT
power project is a positive development, and has once again raised hopes on boosting
other power investments under the BOT approach.
The project also plays an important
role in supplying power to some southern provinces, as there is concern over
the power supply in said provinces due to delays in the Song Hau 1 and Long
Phu 1 thermal power plants.
The Long Phu 1 and Song Hau 1
projects in the Mekong River Delta provinces of Soc Trang and Hau Giang,
respectively, are designed to produce 1,200MW each annually, but are now
years behind schedule. Both of them are invested by Vietnam’s state-run oil
and gas group PetroVietnam.
The Vietnamese government has
pressed ministries to boost coal-fired projects and coal supplies in order to
sufficiently power the southern provinces in the near future. This is
currently considered one of the main challenges the government faces.
Meanwhile, the Hai Duong BOT plant
project spearheaded by Jaks Hai Duong Power Co., Ltd., a joint venture
between Malaysian Jaks Resources Bhd and China Power Engineering Consulting
Group Co., Ltd., expects to come into operation over the next few years since
it started construction in March 2016. The first 600MW turbine of the 1,200MW
plant is expected to be put into operation in 2020.
This is also the first foray of
Malaysian firm Jaks Resources Bhd into Vietnam. Last week, company delegates
also visited the southern province of Binh Phuoc to investigate opportunities
for a 200MW solar project, with investment capital of $262.5 million.
Another Malaysian company, Janakuasa
Sdn Bhd, has signed four landmark documents with Vietnam’s Ministry of
Industry and Trade for the development of the 1,200MW Duyen Hai 2 coal-fired
power plant in the southern province of Tra Vinh, specifically a land-lease
deal, a power purchase agreement, a BOT contract, and a government guarantee.
The project is one of four power
projects within the Duyen Hai Power Centre, which has a combined generation
capacity of 4,348MW, and uses imported coal as the feedstock to generate
power.
A few months ago, a consortium
including Saudi Arabian ACWA Power and Korea’s Taekwang Power Holdings Co.,
Ltd. officially received an investment certificate for the $2.3 billion Nam
Dinh 1 thermal power project, making it the seventh foreign-invested BOT
power project licensed in Vietnam. The project is scheduled to commence
construction in early 2018. The first unit will enter commercial operations
within 51 months.
The list of foreign-invested BOT
power projects will rise further as several foreign firms are currently in
negotiations or are conducting feasibility studies for developing thermal
power plants nationwide. They include Korea’s Samsung C&T Corporation,
India’s Tata Power, Singapore’s Sembcorp Industries, and Thailand’s EGATI.
By Phuong Thu/VIR
|
Thứ Năm, 2 tháng 11, 2017
Đăng ký:
Đăng Nhận xét (Atom)
Không có nhận xét nào:
Đăng nhận xét