Transport Ministry lowers investment estimate for Long
Thanh airport
Admitting
that the initial estimate to build
Minister of Transport Dinh La Thang
said at a National Assembly’s Steering Committee the pre-feasibility study
shows that the investment cost could be cut by $3 billion.
In a report MOT submitted to the
National Assembly in October 2014, it quoted an $18.7 billion investment.
This included $7.8 billion in capital to be invested in the first phase.
However, total investment capital has
been cut to $15.8 billion, of which $5.2 billion would be spent in the first
phase of the project.
The capital for the project would be
sourced from the state budget (VND12.149 trillion), which provides 11.1
percent of the total investment capital, ODA (official development
assistance) (VND29.177 trillion), 26.5 percent, and non-state budget
VND68.644 trillion, 62.4 percent.
The chair of the National Assembly’s
Economics Committee, Nguyen Van Giau, in his project appraisal report, noted
that $5.2 billion may not be the final estimate.
Phung Quoc Hien, chair of the
National Assembly’s Finance & Budget Committee, said the money for the
project would come mostly from the state budget.
“It is estimated that the State would
have to pay VND40.1 trillion out of every VND100 trillion of the total
expenses. And this is just for the first phase of the project,” he said.
“Therefore, it is necessary to clarify the issues relating to the public
debt.”
Even though the NA Economic Committee
agreed with the need to build a new airport, it also raised concerns over the
amount the
Thang said investment capital may be
adjusted several times more, but said the estimates were the maximum amount
of capital needed.
Thang also tried to reassure the
National Assembly’s Deputies by saying that MOT would not need money from the
State budget, if the government allowed it to retain funds to be collected
from the equitization of Long Thanh and Phu Quoc airports.
As for loans from ODA, Thang said
that it is not difficult to borrow money from sources because all airport
projects have been profitable.
Dr. Nguyen Thien Tong from the HCM
City University of Technology noted that the drop in investment by $3 billion
shows that MOT was not careful when drawing up the prefeasibility study.
Therefore, no one can say for sure if $15.8 billion is an accurate figure.
It is quite common for the actual
cost of transport projects to exceeded their original estimates, which is why
many NA deputies are worried about additional unexpected expenses.
Kim Chi, VNN
|
Thứ Ba, 3 tháng 3, 2015
Đăng ký:
Đăng Nhận xét (Atom)
Không có nhận xét nào:
Đăng nhận xét