Chinese-contracted
railway project in Hanoi suffers 57% cost overrun
A section of the under-construction
Cat Linh – Ha Dong urban rail project is seen in Hanoi. Tuoi Tre
A Chinese-sponsored railway project
in Hanoi, whose construction is infamous for causing a series of accidents,
has been hit by yet another scandal as it is expected to cost 57 percent more
than first thought.
The Railway Project Management Unit is seeking approval
from the Ministry of Transport to increase the total investment in the Cat
Linh – Ha Dong urban rail project to US$868.04 million from the previous
estimate of $552.86 million.
The $315.18 million cost overrun is calculated by
Transport Engineering Design Inc. and assessed by the Institute of
Construction Economics under the Ministry of Construction, according to the
project management unit.
The total investment must be hiked because the actual
construction of many units under the project is different from their design,
and there are many extra components, the management unit said.
For instance, while the project is designed to have
two-story terminals, three-story ones have actually been built, which led to
higher construction costs, it elaborated.
The Cat Linh – Ha Dong urban railway project broke
ground in October 2011, with $419 million of the initial investment estimate
covered by China’s official development assistance (ODA) loans.
China will add $250.62 million to cover part of the
$315.18 million cost overrun, whereas the Vietnamese side will increase its
capital contribution to $198.42 million from the previous $133.86 million.
Vietnam will thus have to take a massive $669.62
million ODA loan from China for the project.
The Vietnam Railway Authority, under the transport
ministry, is the project developer, whereas China Railway Sixth Group, a
subsidiary of construction conglomerate China Railway Group, is the EPC
(engineering, procurement, and construction) contractor.
Under an EPC contract, the contractor designs the
installation, procures the necessary materials, and implement the project.
The Railway Project Management Unit said the project
has so far had construction work worth VND5.9 trillion ($263.39 million)
completed, or 66 percent of the initial investment estimate.
Construction of infrastructure for the project will
likely finish by the end of this year and it may officially go on stream in
March 2016.
The Chinese-contracted Cat Linh – Ha Dong urban railway
project has been hit by several scandals since groundbreaking.
The project will use 13 trains provided by China’s
Beijing Rolling Stock Equipment Co. under a $63.2 million supply contract,
which has met with strong objection by local members of the public as well as
experts in the field.
Minister of Transport Dinh La Thang has said it was
“force majeure,” or an unavoidable circumstance, because Vietnam is required
to buy trains made by Chinese companies as per the contract signed with
China.
Also in June, the project was blasted as locals noticed
its rails were ‘wave-like’ and
comparable to those of a roller coaster.
The wavy parts of the railway can easily be seen with
the naked eye, raising safety concerns among local experts and members of the
public.
In August the EPC contractor of the project was
admonished by the Railway Project Management Unit for “causing many accidents
related to labor safety.”
The warning came two days after a bar of steel fell
from a construction site of the project onto a four-seat car traveling below,
almost killing the driver.
TUOI TRE NEWS
|
Thứ Ba, 27 tháng 10, 2015
Đăng ký:
Đăng Nhận xét (Atom)
Không có nhận xét nào:
Đăng nhận xét