Authorities in the Central Highlands
Speaking to the
press earlier this week, Bui Van Cu, vice director of Kon Tum Department of
Industry and Trade, said they regard incident at the Dak Mek 3 Hydropower
Plant as “serious” and proposed that related agencies conduct quality
inspections.
Part of the dam in
Dak Choong Commune, Dak Glei District, suddenly broke on November 22,
crushing Nguyen Viet Hung to death. The 28-year-old worker was driving by
when the collapse occurred.
The collapsed
segment was estimated to be 80 meters long, 20 meters high and 1.5 meters
thick, according a report issued by project’s contractor, the Hong Phat
Mechanics and Construction Company.
Speaking to
Vietweek, Le Ba Thanh, director of the project’s investor, the Hong Phat Dak
Mek Hydropower Company, the dam failed because it could not withstand the
large amount of rock, estimated at 700 cubic meters, which was poured on it
during the height of construction.
But he also said
that they are still waiting for the official conclusions from related
agencies.
Earlier, Thanh was
quoted by Tuoi Tre (Youth) newspaper as saying that the dam was damaged by a
dump truck that crashed into its body.
“We guaranteed
that the dam was built with quality and in accordance with the design,” he
said, acknowledging that the contractor was their member company.
However, in an
interview with the newspaper, Le Van Thinh, chief of the National Agency for
Construction Work’s Quality Assessment, ruled out the possibility that a
crash by a truck, despite weighing 60 tons as claimed by the investor, could
have caused the fatal incident.
The design of a
dam had to be made with considerations about sudden pressures that could be
caused by trucks colliding with the dam during construction, he said.
“Therefore, first
of all, the culpability of the contracted designer and the design itself must
be reviewed,” Thinh stressed.
If it was true
that a truck collision could break a “thick concrete wall,” there must have
been something wrong with the design, according to the official.
Secondly, he said,
it must be determined whether the contractor made mistakes, because some
workers claimed that cracks had appeared prior to the accident and police did
in fact find cracks in other sections of the dam.
According to
Thinh, cracks could be caused by poor quality concrete or a faulty
foundation.
Nguyen Bo,
director of Kon Tum Department of Industry and Trade, told Vietweek that the
investor did not report the accident to the department until three days
later.
Such accidents are
supposed to be reported to district authorities and the Ministry of
Construction within 24 hours, Thinh said.
Construction on
the dam got underway in March 2009 and some 80 percent of the work had
been completed at the time of the collapse, according to Thanh.
The dam was
scheduled to begin operating in the first quarter next year with an
expected output of 7.5 MW and a reservoir capable of storing over 1.7 million
cubic meters, but the accident is likely to delay its start date by more than
two months.
By Tran Hieu, Thanh Nien News
|
Thứ Bảy, 1 tháng 12, 2012
Đăng ký:
Đăng Nhận xét (Atom)
Không có nhận xét nào:
Đăng nhận xét