Construction of Hanoi urban railway project gets tardy
due to indebted Chinese contractor
An
aerial view of the under-construction Cat Linh - Ha Dong urban railway
project in Hanoi.Tuoi Tre
An infamous
Chinese-contracted urban railway project in Hanoi is lagging behind schedule
as the chief contractor is heavily indebted to some sub-contractors.
Progress in
the completion of half of the 12 stops of the Cat Linh – Ha Dong urban
railway is now nine to 22 days slower than slated, Du Giang, the project’s
executive director, admitted at a recent meeting with the Vietnamese Ministry
of Transport.
The Vietnam
Railway Authority, under the transport ministry, is the project developer,
whereas China Railway Sixth Group, a subsidiary of construction conglomerate
China Railway Group, is the EPC (engineering, procurement, and construction)
contractor.
Giang attributed
the sluggish progress to the Lunar New Year holiday that concluded last
month, when workers returned home for celebration and only a few of them got
back to work after that, and a VND400 billion (US$17.86 million) debt the
group owes to its sub-contractors.
The project
director said everything will be resolved if “[we] have money.”
When asked
by Deputy Minister of Transport Nguyen Hong Truong as to who is responsible
for the capital shortage, Giang answered that the EPC contractor is to blame.
The Chinese
side has yet to approve an additional disbursement of $19.2 million as
requested by the main contractor, Giang said.
However,
Trieu Khac Dung, deputy head of the transport ministry’s agency in charge of
construction project quality assurance, said the debt of the contractor is as
huge as VND554 billion ($24.73 million), which led to the tardy progress.
The EPC
contract is running short of money as China is shoring up efforts to halt
cash outflow, which affects the Cat Linh – Ha Dong project, he explained.
Kids look down to the construction site of the urban railway project. Photo: Tuoi Tre
While the
sub-contractors have already brought equipment, machinery and employees to
the construction sites, work could not get started due to the lack of money,
according to the Vietnamese official.
“It is like
getting your gun ready but there are no bullets inside,” Dung said.
Dung thus
suggested that the transport ministry work with the Chinese Embassy in Hanoi
and the Export-Import Bank of China to ask for capital allotment to ensure
progress for the project.
In response,
Giang, the project director, said the EPC contractor will soon work with
relevant Chinese agencies to seek approval for the $19.2 million
disbursement.
He added
that the deputy general director of the China Railway Sixth Group is
scheduled to arrive in Hanoi on Sunday to talk to the transport ministry and
the project management unit about the issue.
Deputy
Minister Truong said relevant sides must ensure the project completion by the
end of this year, and ordered that the sub-contractors continue working while
waiting for the main contractor to clear its debts.
The Cat Linh
– Ha Dong urban railway project broke ground in October 2011, at an initially
estimated investment of $552 million.
In November
2014, the transport ministry proposed that the total investment be increased
to $868.04 million due to a cost overrun during the course of construction.
The project
has been hit by several scandals, including a fatal accident in November
2014, since groundbreaking.
TUOI TRE NEWS
|
Thứ Sáu, 4 tháng 3, 2016
Đăng ký:
Đăng Nhận xét (Atom)
Không có nhận xét nào:
Đăng nhận xét