Someone has
been siphoning construction materials off a major highway project funded by
foreign official development assistance
Only a couple of weeks before the launch of the first section of the Ho Chi Minh City – Long Thanh – Dau Giay Expressway, an ex-worker from the project told Thanh Nien that many of its materials had been siphoned off.
A subsequent
investigation by the paper proved that what the worker, who wants to remain
anonymous, said was true.
The 55-km
The VND20 trillion
(US$950 million) expressway, co-financed by the Asian Development Bank and
Japan Bank for International Cooperation, is part of the 1,811-km
(1,125-mile) north-south expressway project that mostly runs along the
current Highway 1A.
A 20-km section of
the HCMC-Long Thanh - Dau Giay Expressway is expected to open for traffic on
December 30. The rest is expected to be completed in 2014.
The section of the
highway is part of Package 3, located in
Over the past
weeks, a Thanh Nien reporter visited the site
several times and found that a number of concrete and metal barriers and
center dividers were not built following approved designs.
The concrete
blocks, to be buried in the ground to hold metal poles upright, are much
smaller than they should be, and the metal poles have been improperly placed
in the blocks.
According to Le
Manh Hung, director of the project’s management unit, the concrete blocks are
supposed to 1.2 meters long with a diameter of 0.46 meters.
However, many
concrete blocks are only between 0.25-0.6 meters, much shorter than as
designed.
But Hung said the
project supervisor had carefully supervised the project.
“They worked very
carefully and place the metal pole in the middle of the blocks as designed,”
he said.
“When supervising,
we observed and took the pictures of the constructer drilling into the
ground, placing metal frames and the metal pole in the structure before
spilling concrete into it.”
But in reality, Thanh
Nien found
many poles were sloppily installed into the side of the metal block instead
of at center as designed.
A transport
infrastructure expert, who asked to remain unnamed, said builders who do not
strictly follow designs cause great risks.
“If the metal
poles are not placed in the middle of the concrete, it will not have the
ability to withstand force as designed,” he said.
“This is an
unacceptable error for a high quality expressway with a designed speed of up
to 120 kph (75 mph).”
Besides the
reduced size and misplaced poles, many concrete blocks are sloppily made with
rough surfaces and the concrete is not solid.
An expert
experienced in assessing road construction in HCMC said sloppy construction
is one of the ways corrupt people siphon benefits for themselves off a
project.
“The constructor
can cash in from saving time and manpower,” he said.
On December 24,
deputy minister of construction Nguyen Ngoc Dong said his ministry had
instructed the Department of Management of Construction and Quality of
Transport Infrastructure Projects and the project investor – Vietnam
Expressway Corporation – to examine the package.
On the same day,
an inspection team from the two agencies randomly pulled up three poles from
the section in question and found that all of them were attached to
poor-quality concrete blocks that were smaller than designed.
After that, the
inspectors allowed the builder’s representative to choose a pole at his will
for examination.
The concrete block
under the pole he chose was also incorrectly built, with a diameter of 0.3
meters instead of 0.48 as designed. The concrete was also not solid enough.
However, the
inspection team left the site without taking the poles for examination by an
independent party to clarify the matter.
After examining
the scene, the inspection team had a meeting with the constructor at the
latter’s office in
At the meeting,
Nguyen The Vuong, representative of the project’s supervisor and consultant –
a joint venture between Nippon Koei and TEDI South - said that there used to
be two supervisors in charge of overseeing several construction sites of the
package before they assigned only one supervisor.
“Every morning,
the supervisor checked if the construction company dug the holes [for poles]
before supervising other places. When he returned to the site in the evening,
the poles were already buried,” he said.
Who’s who?
Nguyen Van Chu, an
official at the Department of Management of Construction and Quality of
Transport Infrastructure Projects and a member of the inspection team, said
the constructor and supervisor were at fault for the wrongdoings.
“The transport
ministry has instructed the project’s management unit, the constructor and
the supervisor and consultant to report on these cases,” he said.
Hung, the director
of the project’s management unit, said his agency had instructed the builder
to reconstruct the poles as designed.
He also said the
builder is responsible because the package is under construction and has yet
to be assessed and handed over to the investor.
Pham Hong Quang,
VEC deputy director also told Tuoi Tre (Youth) newspaper on December 24 that
the constructor would have to repair relevant damages before December 30,
when the highway is scheduled to open.
“We will consider
taking relevant measures against the project’s management unit, the
constructor and the supervisor and consultant,” he said.
On December 25,
the construction ministry issued a press release on the issue, saying it has
instructed relevant agencies to solve the problems before launching the
highway.
The ministry has
announced it will evaluate the wrongdoings, identify the causes and “issue
strict measures against individuals and entities found responsible” before
December 30.
A source told Thanh
Nien on December 25
that project investor Vietnam Expressway Corporation (VEC) had rebuked
builder Posco E&C, package manager Sang Hoon Lee, construction manager
Cho Yang Cook, as well as the whole Nippon Koei – Tedi South joint
venture and supervisor Dang Quoc Thang.
VEC has asked the
constructor to replace the construction team
and wants the team banned from any further construction on the package.
VEC wants a new team to be assigned to reconstruct the barriers and center
dividers.
By Dam Huy,
Thanh Nien News
|
Thứ Năm, 26 tháng 12, 2013
Đăng ký:
Đăng Nhận xét (Atom)
Không có nhận xét nào:
Đăng nhận xét