First Solar leaves, but its assets still
stay in Vietnam
Arizona-based
First Solar has decided to give up the solar panel project and leave
![]()
Just eight months after the project
kicked off, First Solar announced the suspension of the huge project
capitalized at $1.2 billion after finding out about the oversupply of the
products in the world market. It also hurried to fulfill necessary procedures
to leave
However, the presence of the
The workshops are believed to be
“valuable” as they have been built by the German M+W contractor in accordance
with international standards.
These include the 107,000 square
meters of industrial land which comprises of two production areas, one large
logistic area, and one office building covering an area of 6,000 square
meters. All the items are located in a 23 hectare land plot.
There is also a 21 hectare land plot
with electricity and water supply works which can serve the large scale
production.
The
An official from the HCM City
Industrial Zone and Export Processing Zone Board of Management (Hepza) has
confirmed that the workshops, located in the Dong Nam Industrial Zone in Cu
Chi district, still cannot be transferable due to the legal problems relating
to the land laws, though a lot of foreign investors wish to buy the
workshops.
The official said Hepza is making
every effort to help solve the problems, but he cannot say when exactly the
problems can be settled. The best scenario Hepza wants is that the investors
to buy the workshops are the high technology firms.
In principle, there are two ways the
investor can follow to stop projects. With the first option, it can transfer
the project to other partners. If so, the legal status and the business field
of the First Solar project would still be valid. The only change to be made
is the name of the project investor.
However, analysts believe that it
would be very difficult to find a suitable investor who can replace First
Solar and implement the project as it was initially designed. This is a high
technology project which requires huge investment capital.
With the second option, the investor can
leave
The second scenario could be the
choice of the investor. However, as the Hepza’s representative said, the
problems with the legal procedures have hindered the sale.
In March 2011, First Solar started
the construction of the solar panel factory. In October 2011, it stated the
suspension of the project implementation due to the imbalance in the supply
and demand in the world market.
In July 2012, First Solar offered to
sell workshops.